Project Description: This project involves the evaluation of Pump Station (PS) improvement alternatives, evaluation of 3,500 LF of 6-inch PVC Force Main (FM) rehabilitation/ replacement alternatives, and preparation of a Preliminary Engineering Report (PER). The findings from PER stated that the PS and FM are adequately sized and functioning properly for the service area; however, the PS is receiving excess flow.  City is pursuing to find and fix the source of excess flow before continuing with this project and it has been put on hold. 

Public Benefit: Efficient Operations; Environmental; Regulatory Compliance.

Project Map Project Gallery
  • Project Status
  • Project Schedule
  • Project Events
Design approved by City Council 7/21/20.
Under Design.

Estimated Design Completion Spring 2025.

Estimated Construction Start Winter 2025.

Estimated Construction Completion Fall 2026.